1st case:
No. of men's engaged for work:9
No. of hours:10hrs
work done:1/3
2nd case:
No. of men require for work:(9+x)
Additional Days :2
work to be done: 2/3
Acc. to formula:
(M1*D1)/W1=(M2*D2)/W2
(9*10)/(1/3)=((9+X)*2*3)/2
Upon solving ,u ll get x=81 workers
Knowledge Expert
· commented
· 1 Months ago
In question, 10 days is correct, re-read the solution carefully.