A can do a piece of work in 24 days. When he had worked for 4 days, B joined him. If complete work was finished in 16 days B can alone finish that work in:

Options:
A)

18 days

B)

36 days

C)

72 days

D)

48 days

Solution:

Ans: (b) 

  

  