check the question first for your question answer will be 31. and you have given question wrong

Question:

A, B and C can do a piece of work in 20, 30 and 60 days respectively, they started the work together. If A left the work after working 5 days and B left the work 2 days after A had left. In how many days C will completed the remaining work?

Options:
A)

24 days

B)

12 days

C)

48 days

D)

36 days

Solution:

Ans: (a)

  