volume of mortar = 0.015*100=1.5cum
30% extra for joint filling= 1.5*1.3=1.95cum
25%extra for dry mix= 1.95*1.25=2.4375cum
volume of cement required= 2.4375/7 =0.348

Question:

For 15 mm thick cement plastering 1 : 6 on 100 sq.m, new brick work, the quantity of

cement required is:

Options:
A)

0.200 m3

B)

0.247m3

C)

0.274 m3

D)

0.343m3

Solution:

Ans: (a)