ans should be 12

Question:

A and B can do a work in 8 days. B and C can do the same work in 12 days. If A, B and C can do the same work in 6 days then in how many days can A and C complete the work?

Options:
A)

8

B)

10

C)

12

D)

16

Solution:

Ans: (a)

  