is there any short trick for this

Question:
4 men and 16 women can complete piece of work in 10 days. 10 children and 12 women can complete the same work in 12 days. 5 children and 6 men can complete the same work in 15 days. Then in how many days will thrice the work can be completed by 6 men, 8 women and 20 children? 
Options:
A) 16 days 
B) 20 days 
C) 24 days 
D) 32 days 
Solution:
Ans: (b) 


Knowledge Expert

· commented

· 1 Months ago

Dear Student,

Given solution is already to short, Here three person works in combination of any two so we get different question we have to solve all the equation to find work unit for individual person.