Question:

For a certain loading condition, a saturated clay layer undergoes 40% consolidation in a period of 178 days. What would be the additional time required for further 20% consolidation to occur.

Options:
A)

89 days

B)

222.5 days

C)

329.5 days

D)

400.5 days

Solution:

Ans:(b) 222.5 days