not satisfy the question's statement of both doing in 45/7 days together

Question:

    A completes a work in 8 days less than B. If they worked together and complete in  637    days then B alone can complete it in how many days?


Options:
A)

14  12    days

B)

24 days 

C)

18 days 

D)

16 days 

Solution:

Let A takes x days

B takes x+8 days

So,  1x+1x+8=745   

2x+8x2+8x=745   

7x2+56x=90x+360   

7x2-34x-360=0   

7x2-70x+36x-360=0   

7xx-10+36x-10=0   

x-10=0;7x+36=0   

x=10;x=-367   

So, A takes 10 days

B takes 18 days