Online Courses
Explore
Offline Courses
-
LAW
-
Judiciary
-
Management UG
-
CAT & OMETs
-
CUET
-
Design
-
Architecture
-
UPSC Law Optional
Explore
Test Series
Explore
Resources
-
LAW UG (5 Year LLB)
-
LAW UG (3 Year LLB)
-
LLM + LAW Officer
-
Judiciary
-
Management UG
-
Management PG
-
Design & Arch.
-
NTA CUET [UG]
-
Career Counselling
-
Current Affairs
-
UPSC LAW
Explore
Join Us
Explore
Contact Us
Explore









T THANG BIAKMUAN
· commented
· 1 Months ago
Yachika sharma
· commented
· 1 Months ago
Knowledge Expert
· commented
· 1 Months ago
explanation:-
16 women's work in 1 days = 1/12
1 women's work in 1 days = 1/(12x16)
12 men's work in 1 days = 1/8
1 men's work in 1 days = 1/(12x8)
compare men's work and women's work.
1/(12x16) Women = 1/(12x8) Men.
1 women = 2 Men
16 men's work in 3 days= 1/(12x8) X3x16
= 1/2 work
Remaining work = 1-(1/2) =1/2
10 men left and 4 women joined= 6+2= 8 men because 1 women = 2 Men
8 men's work in 1 day= 1/(12x8)x8
= 1/12 part of work
days for complete 1/2 part of work= 1/(2) / 1/(12)= 6 days.
Hope you have a great learning with us!!