Wages are proportional to work done then wagesxwork =const wrong I think

Question:

By working 6 hours daily 20 workers finish a work in 10 days get Rs.4000 as wages. In how many days 30 workers will complete  the work by working 5 hours daily, when work and wages increased by 60% and 25% respectively –

Options:
A)

16

B)

20

C)

18

D)

24

Solution:

Ans: (a)