Question:
A road of 9 km length will be constructed in 125 days. So 280 workers were employed. But after 75 days it was found that only 5 km road was completed. Now, how many more people were needed to finish the work in the specified time?
Options:
A) 48
B) 44
C) 56
D) 52
Solution:
Ans: (c)