Question:

A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25th of the work is finished. How much additional men be employed, so that the work may be completed on time, each man now working 9 hrs a day?

Options:
A)

34

B)

35

C)

36

D)

37

Solution:

Ans: (b)