it will be 25 days only

Question:

A can do a piece of work in 24 days, B in 52 days and C in 64 days. All being to do it together, but A leaves after 6 days and B leaves 6 days before the completion of the work. How many days did the work last (approx.) ?

Options:
A)

25

B)

20

C)

18

D)

30

Solution:

Ans: (a)

  

Knowledge Expert

· commented

· 1 Months ago

n=720/29
n=24.8 days that is approximately 25 days.
Regards
TR