Question:

5 men can prepare 10 toys in 6 days working 6 hours a day. Then in how many days can 12 men prepare 16 toys working 8 hrs a day?

Options:
A) 5 days    
B) 3 days
C) 4 days  
D) 6 days
E) None of these
Solution:

kanhaiya jha

· commented

· 1 Months ago

Hi, its right..

5 men can prepare 10 toys in 6 days working 6 hours a day. Then in how many days can 12 men prepare 16 toys working 8 hrs a day?

formula is work/capacity = days

(m1 d1 h1)/w1 = (m2 d2 h2)/w2

so, m1 d1 h1 w2 = m2 d2 h2 w1

5*6*6*16 = 12*d2*8*10


so, d2=3 days