Online Courses
-
Law UG
-
Management UG
-
CUET UG
-
Design & Architecture
-
Judiciary Exams
-
3 Year LLB
-
Law PG
-
CAT & OMETs
-
Mentorship
-
Career Counselling
Offline Courses
-
LAW
-
Judiciary
-
Management UG
-
CAT & OMETs
-
CUET
-
Design
-
Architecture
-
UPSC Law Optional
Test Series
-
LAW UG (3 Year LLB)
-
LAW UG (5 Year LLB)
-
Judiciary
-
Judiciary Study Material (JSM)
-
Chhattisgarh (CGPSC)
-
Haryana (HJS)
-
Uttar Pradesh (UP PCSJ)
-
Rajasthan (RJS)
-
Madhya Pradesh [MP]
-
Delhi [DJS]
-
Bihar [BPSC]
-
Uttarakhand [UKPSC]
-
Jharkhand [JKPSC]
-
Gujarat(GJS)
-
Himachal Pradesh [HPPSC]
-
Judiciary [All States]
-
MP ADPO
-
Bihar APO
-
UP APO
-
Haryana ADA
-
Rajasthan APO
-
CGPSC ADPO
-
-
LAW PG + Banking
-
Management UG
-
Management PG
-
NTA CUET
-
Scholarship Tests
-
Design and Arch.
-
All India Tests
-
LE Champions Batch Selection Test
-
SuperGrads CAT Diagnostic Test
Resources
-
LAW UG (5 Year LLB)
-
LAW UG (3 Year LLB)
-
LLM + LAW Officer
-
Judiciary
-
Management UG
-
Management PG
-
Design & Arch.
-
NTA CUET [UG]
-
Career Counselling
-
Current Affairs
-
UPSC LAW
Join Us
Contact Us
Book Store







Knowledge Expert
· commented
· 1 Months ago
Work done by A and B together in 1 day = 1/15 ………….(1)
Work done by B and C together in 1 day = 1/20 ………….(2)
Work done by C and A together in 1 day = 1/30 ………….(3)
Add Eq. 1, 2 and 3.
Work done by 2(A +B + C) together in 1 day = 1/15 + 1/20 +1/30 = 9/60
Work done by (A + B + C) together in 1 day = 9/120
Work done by C in 1 day =9/120 – 1/15 = 1/120
Time taken by C alone = 120 days.
Knowledge Expert
· commented
· 1 Months ago
Work done by 2(A +B + C) together in 1 day = 1/15 + 1/20 +1/30 = 9/60
Work done by (A + B + C) together in 1 day = (9/60)*(1/2) = 9/120