ans should be 18 painter required. please check this

Question:
If 12 painters painted 120 paintings in 30 days, then how many painters will be required to paint 240 painting in 40 days?
Options:
A) 30 Painters.
B) 32 painters.
C) 34 Painters.
D) 36 Painters.
E) None of these.
Solution:

Knowledge Expert

· commented

· 1 Months ago

Dear Student,
The required correction has been done.
Keep learning with us
Thank You
Team Toprankers

Knowledge Expert

· commented

· 1 Months ago

Here painting is work done. Hence this will not be multiplied by 30 or 40 rather it will be 120/30 : 240/40 = 12/x. Hence the solution is wrong. It will be 18 painters.